On Wed, Jul 29, 2009 at 8:51 AM, shaker Khzym
<..hidden..> wrote:
Dear all,
Hello, I have a question about 1.3 , is it ready to work now or there are some work .
Minor things need to be finished up/corrected for beta 1 Some things work very well. Other things don't work quite so well. If you are interested in using it in production at this early state send me an email with exactly what parts of the software you use.
My second question , what is the meaning of Milestone 1/2/3.
Milestone 1 includes the basic AP and Payment interface as well as the Voucher system, permissions, etc.
Milestone 2 includes enhancements to the above, and the draft system
Milestone 3 includes the new reconciliation stuff, and user management.
The next 1.3 release will be beta 1.
Best Wishes,
Chris Travers